[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104887":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104887,780,2,"多选题","下列目标控制措施中，属于经济措施的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","编制和实施资金使用计划",true,{"key":16,"text":17,"correct":14},"B","审核工程量及工程结算报告",{"key":19,"text":20,"correct":14},"C","对工程变更方案进行技术经济分析",{"key":22,"text":23,"correct":24},"D","选择合理的承发包模式和合同计价方式",false,{"key":26,"text":27,"correct":14},"E","进行投资偏差分析和未完工程投资预测","ABCE","本题考查的是目标控制。经济措施。无论是对建设工程造价目标实施控制，还是对建设工程质量、进度目标实施控制，都离不开经济措施。经济措施不仅仅是审核工程量、工程款支付申请及工程结算报告，还需要编制和实施资金使用计划，对工程变更方案进行技术经济分析等。而且通过投资偏差分析和未完工程投资预测，可发现一些可能引起未完工程投资增加的潜在问题，从而便于以主动控制为出发点，采取有效措施加以预防。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]