[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104868":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104868,780,2,"多选题","下列工作内容中，属于建设工程目标动态控制过程的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":18},"B","计划",true,{"key":20,"text":21,"correct":18},"C","执行",{"key":23,"text":24,"correct":18},"D","检查",{"key":26,"text":27,"correct":14},"E","协调","BCD","⒈三大目标动态控制过程 建设工程目标体系构建后，建设工程监理工作的关键在于动态控制PDCA (计划；执行；检查；纠偏)。为此，需要在建设工程实施过程中监测实施绩效，并将实施绩效与计划目标进行比较，采取有效措施纠正实施绩效与计划目标之间的偏差，力求使建设工程实现预定目标。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]