[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104844":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104844,780,2,"多选题","（2020年真题）根据《建设工程监理规范》，需要经建设单位审批的监理文件资料有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单位工程竣工验收报审表",false,{"key":16,"text":17,"correct":18},"B","工程复工报审表",true,{"key":20,"text":21,"correct":14},"C","分部工程报验表",{"key":23,"text":24,"correct":18},"D","工程款支付报审表",{"key":26,"text":27,"correct":18},"E","工程最终延期报审表","BDE","教材页码P154-158 工程复工报审表：经审查符合要求的，总监理工程师应及时签署审查意见，并报建设单位批准后签发《工程复工令》。 工程款支付报审表：项目监理机构对施工单位的申请事项进行审核并签署意见，经建设单位批准后方可由总监理工程师签发《工程款支付证书》。 工程临时或最终延期报审表：项目监理机构对施工单位的申请事项进行审核并签署意见，经建设单位批准后方可延长合同工期。《工程临时或最终延期报审表》需要由总监理工程师签字，并加盖执业印章。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]