[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104837":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104837,780,2,"多选题","监理工作总结包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","向总监理工程师提交的工作总结",false,{"key":16,"text":17,"correct":18},"B","向监理单位提交的工作总结",true,{"key":20,"text":21,"correct":14},"C","向政府有关部门提交的工作总结",{"key":23,"text":24,"correct":18},"D","向建设单位提交的监理工作总结",{"key":26,"text":27,"correct":14},"E","向资质年检部门提交的工作总结","BD","2020版教材P158-161 当监理工作结束时，项目监理机构应向建设单位和工程监理单位提交监理工作总结。因此，本题的正确答案为BD。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]