[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104834":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104834,780,2,"多选题","监理文件档案经（ ）程序后，必须使用科学的分类方法进行存放，这样既可满足项目实施过程查阅、求证的需要，又方便项目竣工后文件和档案的归档和移交。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","收文",true,{"key":16,"text":17,"correct":14},"B","发文",{"key":19,"text":20,"correct":14},"C","登记",{"key":22,"text":23,"correct":14},"D","传阅工作",{"key":25,"text":26,"correct":27},"E","作废",false,"ABCD","2020版教材P162-168 本题考查重点是“建设工程监理文件资料分类存放”。 建设工程监理文件资料经收／发文、登记和传阅工作程序后，必须进行科学的分类后进行存放。这样既可以满足工程项目实施过程中查阅、求证的需要，又便于工程竣工后文件资料的归档和移交。项目监理机构应备有存放监理文件资料的专用柜和用于监理文件资料分类存放的专用资料夹。大中型工程项目监理信息应采用计算机进行辅助管理",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]