[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104830":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104830,780,2,"多选题","下列监理文件资料中，需要建设单位审批同意的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程开工报审表",true,{"key":16,"text":17,"correct":18},"B","工程暂停令",false,{"key":20,"text":21,"correct":14},"C","费用索赔报审表",{"key":23,"text":24,"correct":18},"D","单位工程竣工验收报审表",{"key":26,"text":27,"correct":14},"E","工程临时或最终延期报审表","ACE","2020教材P154-158 下列表式需要建设单位审批同意: (1) B. 0.1 施工组织设计或(专项)施工方案报审表(仅对超过一定规模的危险性较大的分部分项工程专项施工方案) ; (2) B.0.2 工程开工报审表; (3) B.0. 3 工程复工报审表; (4) B. 0.11 工程款支付报审表; (5) B. 0.13 费用索赔报审表; (6) B. 0.14 工程临时或最终延期报审表。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]