[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104825":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104825,780,2,"多选题","根据《建设工程监理规范》GB／T 50319--2013，需要由总监理工程师签字并加盖执业印章的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程款支付报审表",true,{"key":16,"text":17,"correct":18},"B","分部工程报验表",false,{"key":20,"text":21,"correct":18},"C","施工进度计划报审表",{"key":23,"text":24,"correct":18},"D","工程材料、构配件、设备报审表",{"key":26,"text":27,"correct":14},"E","工程临时延期报审表","AE","2020教材P154-158 下列表式应由总监理工程师签字并加盖执业印章: (1) A. 0. 2 工程开工令; (2) A. 0.5 工程暂停令; (3) A. 0. 7 工程复工令; (4) A. 0. 8 工程款支付证书; (5) B. 0. 1 施工组织设计或(专项)施工方案报审表; (6) B. 0. 2 工程开工报审表; (7) B.0. 10 单位工程竣工验收报审表; (8) B. 0. 11 工程款支付报审表; (9) B. 0.13 费用索赔报审表; (10) B. 0. 14 工程临时或最终延期报审表。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]