[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104796":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104796,780,2,"多选题","根据《建设工程监理规范》（GB\u002FT50319-2013），下列监理文件资料中，需要由总监理工程师签字并加盖执业印章的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程款支付报审表",true,{"key":16,"text":17,"correct":18},"B","分部工程报验表",false,{"key":20,"text":21,"correct":18},"C","施工进度计划报审表",{"key":23,"text":24,"correct":18},"D","工程材料、构配件、设备报审表",{"key":26,"text":27,"correct":14},"E","工程临时延期报审表","AE","⒉由总监理工程师签字并加盖执业印章的表式 ⑴A.0.2 工程开工令； ⑵A.0.5 工程暂停令； ⑶A.0.7 工程复工令； ⑷A.0.8 工程款支付证书； ⑸B.0.1 施工组织设计或(专项)施工方案报审表； ⑹ B.0.2 工程开工报审表； ⑺B.0.10 单位工程竣工验收报审表； ⑻B.0.11 工程款支付报审表； ⑼B.0.13 费用索赔报审表； ⑽B.0.14 工程临时或最终延期报审表。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]