[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104775":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104775,780,2,"多选题","(2011年真题）对每一个建设工程的风险都从头开始识别，该做法的缺点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不利于专业风险识别人员积累经验",false,{"key":16,"text":17,"correct":18},"B","耗费时间和精力，风险识别工作效率低",true,{"key":20,"text":21,"correct":18},"C","可能导致风险识别的随意性",{"key":23,"text":24,"correct":14},"D","不利于按时间维对建设工程风险进行分解",{"key":26,"text":27,"correct":18},"E","不便积累风险识别的成果资料","BCE","本题考核初始清单法。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]