[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104773":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104773,780,2,"多选题","(2010年真题）损失控制计划系统中的灾难计划，应至少满足（ ）等要求。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","安全撤离现场人员",true,{"key":16,"text":17,"correct":14},"B","援救及处理伤亡人员",{"key":19,"text":20,"correct":14},"C","控制事故发展和减少资产损害措施",{"key":22,"text":23,"correct":24},"D","调整施工进度计划方案",false,{"key":26,"text":27,"correct":24},"E","调整材料和设备采购计划方案","ABC","本题考核损失控制计划系统中灾难计划的内容。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]