[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104756":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104756,780,2,"多选题","在建设工程风险初始清单中，政治法律风险因素的典型风险事件有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","骚乱",true,{"key":16,"text":17,"correct":14},"B","战争",{"key":19,"text":20,"correct":21},"C","通货膨胀",false,{"key":23,"text":24,"correct":14},"D","经济制裁",{"key":26,"text":27,"correct":14},"E","法律法规的变化","ABDE","2020版教材P171-180 本题考查的是建设工程风险管理。建设工程风险初始清单中，政治法律风险因素的典型风险事件有：法律法规的变化，战争、骚乱、罢工、经济制裁或禁运等。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]