[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104711":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104711,780,2,"多选题","下列建设工程组织管理模式中，不能独立存在的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总承包模式",false,{"key":16,"text":17,"correct":14},"B","EPC模式",{"key":19,"text":20,"correct":14},"C","CM模式",{"key":22,"text":23,"correct":24},"D","Partnering模式",true,{"key":26,"text":27,"correct":24},"E","ProjectControlling模式","DE","2020版教材P198-201 本题考查的是2020版教材Partnering模式。2020版教材Partnering和2020版教材Proj ect Controlling模式并不能作为一种独立存在的模式。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]