[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104679":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104679,780,2,"多选题","施工单位签订的合同主要有（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","材料设备采购合同",true,{"key":16,"text":17,"correct":14},"B","工程分包合同",{"key":19,"text":20,"correct":14},"C","运输合同",{"key":22,"text":23,"correct":14},"D","加工合同",{"key":25,"text":26,"correct":27},"E","工程监理合同",false,"ABCD","2020版教材P8-9 施工单位作为工程承包合同的履行者，也可通过签订合同将工程承包合同中所确定的工程设计、施工、材料设备采购等部分任务委托给其他相关单位来完成，相应的合同有:工程分包合同、材料设备采购合同、运输合同、加工合同、租赁合同、劳务分包合同、保险合同等。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]