[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104618":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104618,780,2,"多选题","根据《合同法》，在工程项目合同体系中，（ ）是两个最主要的节点。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工单位",true,{"key":16,"text":17,"correct":18},"B","监理单位",false,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":14},"D","建设单位",{"key":26,"text":27,"correct":18},"E","分包单位","AD","本题考查的是工程项目合同体系。在工程项目合同体系中，建设单位和施工单位是两个最主要的节点。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]