[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104614,780,2,"多选题","根据《关于实行建设项目法人责任制的暂行规定》，项目总经理的职权有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","负责筹措建设资金",false,{"key":16,"text":17,"correct":18},"B","组织编制项目初步设计文件",true,{"key":20,"text":21,"correct":18},"C","组织项目后评价",{"key":23,"text":24,"correct":18},"D","组织单项工程预验收",{"key":26,"text":27,"correct":14},"E","提出项目开工报告","BCD","2020版教材P6-7 本题考查的是项目法人责任制。选项AE属于项目董事会的职权。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]