[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104608":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104608,780,2,"多选题","下列工作中，属于建设准备工作的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","准备必要的施工图纸",true,{"key":16,"text":17,"correct":14},"B","办理施工许可手续",{"key":19,"text":20,"correct":21},"C","组建生产管理机构",false,{"key":23,"text":24,"correct":14},"D","办理工程质量监督手续",{"key":26,"text":27,"correct":21},"E","审查施工图设计文件","ABD","考点:建设实施阶段的工作内容。工程项目在开工建设之前要切实做好各项准备工作，其主要内容包括：（1）征地、拆迁和场地平整；（2）完成施工用水、电、通信、道路等接通工作；（3）组织招标选择工程监理单位、施工单位及设备、材料供应商；（4）准备必要的施工图纸；（5）办理工程质量监督和施工许可手续。选项C属于生产准备工作；选项E属于勘察设计工作。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]