[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104598":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104598,780,2,"多选题","根据《合同法》，施工企业可单方解除合同的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位违约致使合同目的不能实现",true,{"key":16,"text":17,"correct":18},"B","建设单位交付的施工图设计文件深度不足",false,{"key":20,"text":21,"correct":14},"C","地震导致合同无法履行",{"key":23,"text":24,"correct":18},"D","建设单位迟延3日给付预付款",{"key":26,"text":27,"correct":18},"E","建设单位提供的地质资料不准确","AC","考点:《合同法》主要内容。依据《合同法》第94条，当事人可以解除合同的情形包括：（1）因不可抗力致使不能实现合同目的；（2）在履行期限届满之前，当事人一方明确表示或者以自己的行为表明不履行主要债务；（3）当事人一方迟延履行主要债务，经催告后在合理期限内仍未履行；（4）当事人一方迟延履行债务或者有其他违约行为致使不能实现合同目的；（5）法律规定的其他情形。通常情况下，选项BDE不足以导致解除合同。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]