[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104542":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104542,780,2,"多选题","建设工程监理投标中，用决策树法进行投标决策时，其决策过程包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据已知情况绘出决策树",true,{"key":16,"text":17,"correct":18},"B","计算事件的概率",false,{"key":20,"text":21,"correct":14},"C","计算期望值",{"key":23,"text":24,"correct":14},"D","确定决策方案",{"key":26,"text":27,"correct":18},"E","计算均方差","ACD","考点:建设工程监理投标工作内容。用决策树法分析，其决策过程包括：（1）先根据已知情况绘出决策树；（2）计算期望值；（3）确定决策方案。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]