[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104520":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104520,780,2,"多选题","监理工作完成后，项目监理机构向建设单位提交的监理工作总结内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建设工程监理合同履行情况概述",true,{"key":16,"text":17,"correct":14},"B","由建设单位提供的供项目监理机构使用的办公用房清单",{"key":19,"text":20,"correct":14},"C","监理任务或监理目标完成情况评价",{"key":22,"text":23,"correct":14},"D","表明工程监理工作终结的说明",{"key":25,"text":26,"correct":27},"E","工程监理工作的经验",false,"ABCD","考点:建设工程监理实施程序和原则。监理工作完成后，项目监理机构向建设单位提交的监理工作总结的主要内容除选项ABCD外，还包括：由建设单位提供的供项目监理机构使用的车辆、试验设施等的清单等。选项E属于项目监理机构向工程监理单位提交的监理工作总结的内容之一。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]