[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104508,780,2,"多选题","监理实施细则的内容之一是监理工作方法与措施，根据措施实施内容不同，可将监理工作措施分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","技术措施",true,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","组织措施",{"key":22,"text":23,"correct":24},"D","事前控制措施",false,{"key":26,"text":27,"correct":14},"E","合同措施","ABCE","考点:监理实施细则主要内容。根据措施实施内容不同，可将监理工作措施分为技术措施、经济措施、组织措施和合同措施；根据措施实施时间不同，可将监理工作措施分为事前控制措施、事中控制措施及事后控制措施。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]