[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104497":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104497,780,2,"多选题","在监理规划中，工程进度控制的技术措施有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","落实进度控制的责任",false,{"key":16,"text":17,"correct":14},"B","建立进度控制协调制度",{"key":19,"text":20,"correct":21},"C","建立多级网络计划体系",true,{"key":23,"text":24,"correct":14},"D","对工期提前者实行奖励",{"key":26,"text":27,"correct":21},"E","监控施工单位的实施作业计划","CE","考点:监理规划主要内容。工程进度控制的具体措施：（1）组织措施：落实进度控制的责任，建立进度控制协调制度。（2）技术措施：建立多级网络计划体系，监控施工单位的实施作业计划。（3）经济措施：对工期提前者实行奖励；对应急工程实行较高的计件单价；确保资金的及时供应等。（4）合同措施：按合同要求及时协调有关各方的进度，以确保建设工程的形象进度。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]