[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104485":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104485,780,2,"多选题","建设工程三大目标控制的组织措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定建设工程发包组织管理模式",false,{"key":16,"text":17,"correct":18},"B","明确目标控制人员的任务和职责分工",true,{"key":20,"text":21,"correct":18},"C","建立健全实施动态控制的组织机构.规章制度和人员",{"key":23,"text":24,"correct":18},"D","改善目标控制工作流程",{"key":26,"text":27,"correct":14},"E","在整个建设工程实施过程中，采用信息化技术实施动态控制","BCD","考点:目标控制。组织措施是其他各类措施的前提和保障。包括：建立健全实施动态控制的组织机构、规章制度和人员，明确各级目标控制人员的任务和职责分工，改善建设工程目标控制的工作流程；建立建设工程目标控制工作考评机制，加强各单位（部门）之间的沟通协作；加强动态控制过程中的激励措施，调动和发挥员工实现建设工程目标的积极性和创造性等。选项A属于合同措施；选项E属于技术措施。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]