[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104472":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104472,780,2,"多选题","下列关于建设工程目标控制技术措施的表述中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","需要对各种技术数据进行审核.比较",true,{"key":16,"text":17,"correct":14},"B","需要对施工组织设计进行审查.论证",{"key":19,"text":20,"correct":21},"C","技术措施必须与经济措施结合使用才能取得好的效果",false,{"key":23,"text":24,"correct":14},"D","需要采用工程网络计划技术.信息化技术等实施动态控制",{"key":26,"text":27,"correct":21},"E","技术措施是其他各类措施的前提","ABD","考点:目标控制。为实现三大目标控制，采取的技术措施包括：需要对各种技术数据进行审核、比较，需要对施工组织设计、施工方案等进行审查、论证等。需要采用工程网络计划技术、信息化技术等实施动态控制。选项E错误，应为“组织措施是其他各类措施的前提和保障”。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]