[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104464":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104464,780,2,"多选题","根据《建设工程监理规范》GB\u002FT 50319-2013，关于监理基本表式的表述中，正确的有（ ）。 A.工程监理单位用表（B类表）共有12个 B.施工组织设计或（专项）施工方案报审表（表 B.0.1）均不需要建设单位审批 C.监理通知回复单（表",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","0.9）一般可由原发出《监理通知单》的专业监理工程师核查签认，重大问题可由总监核查签认",false,{"key":16,"text":17,"correct":14},"B","工程临时或最终延期报审表（表",{"key":19,"text":20,"correct":21},"C","0.14）由总监理工程师签发，签发前应征得建设单位批准同意",true,{"key":23,"text":24,"correct":21},"D","分包单位资格报审表（表",{"key":26,"text":27,"correct":14},"E","0.4）由施工单位报送监理单位，专业监理工程师签署意见即可","CD","考点:建设工程监理基本表式及其应用说明。选项A错误，工程监理单位用表（A类表）共有8个；选项B错误，施工单位报送的表B.0.1，对于超过一定规模的危险性较大的分部分项专项施工方案，需要报送建设单位审批；选项E错误，分包单位资格报审表（A3）由施工单位报送监理单位，由专业监理工程师提出审查意见后，由总监理工程师审核签认。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]