[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104450":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104450,780,2,"多选题","工程设计进度计划的审查内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","相应设计人员的配置安排是否合理",true,{"key":16,"text":17,"correct":14},"B","计划中各个节点是否存在漏项",{"key":19,"text":20,"correct":14},"C","出图节点是否符合建设工程总体计划进度节点要求",{"key":22,"text":23,"correct":14},"D","各专业计划的衔接是否合理",{"key":25,"text":26,"correct":27},"E","设计任务书的完成情况",false,"ABCD","考点:勘察设计阶段服务内容。工程设计进度计划的审查内容包括：（1）计划中各个节点是否存在漏项；（2）出图节点是否符合建设工程总体计划进度节点要求；（3）分析各阶段、各专业工种设计工作量和工作难度，并审查相应设计人员的配置安排是否合理；（4）各专业计划的衔接是否合理，是否满足工程需要。选项E属于工程设计成果的审查内容。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]