[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104423":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104423,780,2,"多选题","下列关于风险型CM模式的表述中，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","GMP低于合理值时，CM单位承担的风险就增大",true,{"key":16,"text":17,"correct":14},"B","GMP具体数额的确定是CM合同谈判的一个焦点和难点",{"key":19,"text":20,"correct":14},"C","签订CM合同时，合同价尚不是一个确定的具体数据，主要是确定计价原则和方式",{"key":22,"text":23,"correct":24},"D","CM单位与承包商是分包关系",false,{"key":26,"text":27,"correct":24},"E","CM单位介入工程时间较晚","ABC","考点:CM模式。选项D错误，风险型CM模式中，CM单位与承包商并不是真正意义上的分包关系；选项E错误，CM单位介入工程时间较早。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]