[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104419":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104419,780,2,"多选题","以下关于非代理型CM模式的表述中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","CM单位对设计单位有指令权",false,{"key":16,"text":17,"correct":18},"B","业主可能与少数施工单位和材料.设备供应单位签订合同",true,{"key":20,"text":21,"correct":18},"C","CM单位在设计阶段就参与工程实施",{"key":23,"text":24,"correct":14},"D","CM单位与施工单位之间是总分包关系",{"key":26,"text":27,"correct":18},"E","GMP的具体数额是CM合同谈判中的焦点和难点","BCE","考点:CM模式。CM单位对设计单位没有指令权，只能向设计单位提出一些合理化建议，他们之间是协调管理关系。CM单位与施工单位之间似乎是总分包关系，但实际上却与总分包模式有本质的不同。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]