[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1104395,780,1,"单选题","(2019年真题)建设工程新开工时间是指工程设计文件中规定的任何一项永久性工程的（ ）开始日期",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地质勘察",false,{"key":16,"text":17,"correct":14},"B","场地旧建筑物拆除",{"key":19,"text":20,"correct":14},"C","施工用临时道路施工",{"key":22,"text":23,"correct":24},"D","正式破土开槽",true,"建设工程新开工时间是指工程设计文件中规定的任何项永久性工程第一次正式破土开槽的开始日期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]