[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1104389,780,1,"单选题","(2012年真题)关于建设程序中各阶段工作的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在初步设计或技术设计的基础上进行施工图设计，使其达到施工安装的要求",false,{"key":16,"text":17,"correct":18},"B","工程开始拆除旧建筑物和搭建临时建筑物时即可算作工程的正式开工",true,{"key":20,"text":21,"correct":14},"C","生产准备阶段是由建设阶段转入生产经营阶段的重要衔接阶段",{"key":23,"text":24,"correct":14},"D","竣工验收是考核建设成果、检验设计和施工质量的关键步骤","建设工程新开工时间是指工程设计文件中规定的任何一项永久性工程第一次正式破土开槽的开始日期。不需要开槽的工程，以正式开始打桩的日期作为开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]