[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1104388,780,1,"单选题","(2011年真题)某工程，施工单位于3月10日进入施工现场开始搭设临时设施，3月15日开始拆除旧有建筑物，3月25日开始永久性工程基础正式打桩，4月10日开始平整场地。该工程的开工时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3月10日",false,{"key":16,"text":17,"correct":14},"B","3月15日",{"key":19,"text":20,"correct":21},"C","3月25日",true,{"key":23,"text":24,"correct":14},"D","4月10日","不需要开槽的工程，以正式开始打桩的日期作为开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]