[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1104375,780,1,"单选题","工程建设程序中设计紧后的程序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","策划",false,{"key":16,"text":17,"correct":18},"B","施工",true,{"key":20,"text":21,"correct":14},"C","技术设计",{"key":23,"text":24,"correct":14},"D","交付使用","2020版教材P10 本题考查的是工程建设程序。工程建设程序是指建设工程从策划、决策、设计、施工，到竣工验收、投入生产或交付使用的整个建设过程中，各项工作必须遵循的先后顺序。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]