[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1104374,780,1,"单选题","工程项目在开工建设之前，要切实做好各项准备工作不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组建生产管理机构",true,{"key":16,"text":17,"correct":18},"B","征地、拆迁和场地平整",false,{"key":20,"text":21,"correct":18},"C","准备必要的施工图纸",{"key":23,"text":24,"correct":18},"D","办理工程质量监督和施工许可手续","2020版教材P12 本题考查的是工程建设程序。 工程项目在开工建设之前，要切实做好各项准备工作。 其中包括：征地、拆迁和场地平整；完成施工用水、电、通信、道路等接通工作；组织招标选择工程监理单位、施工单位及设备、材料供应商；准备必要的施工图纸；办理工程质量监督和施工许可手续。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]