[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1104370,780,1,"单选题","如果初步设计提出的总概算超过可行性研究报告总投资的（）以上或其他主要指标需要变更时，应说明原因和计算依据，并重新向原审批单位报批可行性研究报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":18},"B","10%",true,{"key":20,"text":21,"correct":14},"C","15%",{"key":23,"text":24,"correct":14},"D","20%","2020版教材P12 本题考查的是工程建设程序。如果初步设计提出的总概算超过可行性研究报告总投资的10%以上或其他主要指标需要变更时，应说明原因和计算依据，并重新向原审批单位报批可行性研究报告。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]