[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1104363,780,1,"单选题","工程总承包项目经理职责不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","代表企业组织实施工程总承包项目管理，对实现合同约定的项目目标负责",false,{"key":16,"text":17,"correct":18},"B","制订项目管理目标责任书",true,{"key":20,"text":21,"correct":14},"C","对项目实施全过程进行策划、组织、协调和控制",{"key":23,"text":24,"correct":14},"D","负责组织项目的管理收尾和合同收尾工作","本题考查的是工程总承包模式。工程总承包项目经理应履行下列职责：（1）执行工程总承包单位管理制度，维护企业合法权益；（2）代表企业组织实施工程总承包项目管理，对实现合同约定的项目目标负责；（3）完成项目管理目标责任书规定的任务；（4）在授权范围内负责与项目干系人的协调，解决项目实施中出现的问题；（5）对项目实施全过程进行策划、组织、协调和控制；（6）负责组织项目的管理收尾和合同收尾工作。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]