[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1104347,780,1,"单选题","如果初步设计提出的总概算超过可行性研究报告中总投资估算的（）以上或其他主要指标需要变更时，应当重新向原审批单位报批可行性研究报告。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":14},"B","5%",{"key":19,"text":20,"correct":14},"C","9%",{"key":22,"text":23,"correct":24},"D","10%",true,"2020版教材P11-13 如果初步设计提出的总概算超过可行性研究报告总投资的10%以上或其他主要指标需要变更时，应说明原因和计算依据，并重新向原审批单位报批可行性研究报告。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]