[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1104346,780,1,"单选题","需要进行大量土石方工程的铁路工程，以()作为正式开工日期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","任何一项永久性工程第一次正式破土开槽的开始日期",false,{"key":16,"text":17,"correct":14},"B","临时建筑开始施工的日期",{"key":19,"text":20,"correct":14},"C","正式开始打桩的日期",{"key":22,"text":23,"correct":24},"D","开始进行土石方工程施工日期",true,"2020版教材P11-13 本题考查的是工程建设程序。需要进行大量土石方工程的铁路工程，以开始进行土石方工程施工日期作为正式开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]