[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1104315,780,1,"单选题","（2020年真题）根据《招标投标法》，招标人对已发出的招标文件进行必要的澄清时，应在提交投标文件截止时间至少（ ）日前，以书面形式通知所有招标文件收受人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","15",true,{"key":23,"text":24,"correct":14},"D","20","教材页码P20-37 招标人对已发出的招标文件进行必要的澄清或者修改的，应当在招标文件要求提交投标文件截止时间至少15日前，以书面形式通知所有招标文件收受人。该澄清或者修改的内容为招标文件的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]