[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1104200,780,1,"单选题","下列选项中，属于监理单位工程进度控制内容的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","参加工程竣工验收",false,{"key":16,"text":17,"correct":14},"B","编写工程质量评估报告",{"key":19,"text":20,"correct":14},"C","对实际完成量与计划完成量进行比较分析",{"key":22,"text":23,"correct":24},"D","比较分析工程施工实际进度与计划进度，预测实际进度对工程总工期的影响",true,"2020版教材P53-55 工程进度控制包括：审查施工单位报审的施工总进度计划和阶段性施工进度计划；检查施工进度计划的实施情况；比较分析工程施工实际进度与计划进度，预测实际进度对工程总工期的影响等。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]