[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1104101,780,1,"单选题","建设单位领取了施工许可证，但因故不能按期开工，应当向发证机关申请延期，延期( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以两次为限，每次不超过3个月",true,{"key":16,"text":17,"correct":18},"B","以一次为限，最长不超过3个月",false,{"key":20,"text":21,"correct":18},"C","以两次为限，每次不超过1个月",{"key":23,"text":24,"correct":18},"D","以一次为限，最长不超过1个月","2020版教材P20-37 因故不能按期开工的，应当向发证机关申请延期;延期以两次为限，每次不超过3个月。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]