[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1104025,780,1,"单选题","以下各项中，关于委托人义务的表述中，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","委托人更换委托人代表时，应提前14天电话通知监理人",true,{"key":16,"text":17,"correct":18},"B","委托人应在收到预付款支付申请后28天内，将预付款支付给监理人",false,{"key":20,"text":21,"correct":18},"C","符合专用合同条款约定的开始监理条件的，委托人应提前7天向监理人发出开始监理通知",{"key":23,"text":24,"correct":18},"D","监理服务期限自开始监理通知中载明的开始监理日期起计算","考点:建设工程监理合同履行。选项A错误，委托人更换委托人代表的，应提前14天将更换人员的姓名、职务、联系方式、授权范围和授权期限书面通知监理人。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]