[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1104011,780,1,"单选题","监理单位如对于某类工程的工期很有信心，可作出对招标人有利的保证，靠此吸引招标人的注意，同时向招标人提出保证措施和惩罚性条款，确保承诺的可实施性，这体现了常用投标策略中（ ）的策略。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以投标报价取胜",false,{"key":16,"text":17,"correct":14},"B","以信誉和口碑取胜",{"key":19,"text":20,"correct":21},"C","以缩短工期等承诺取胜",true,{"key":23,"text":24,"correct":14},"D","适应长远发展的策略","2020版教材P78-82 本题考查的是建设工程监理投标策略。以缩短工期等承诺取胜：工程监理单位如对于某类工程的工期很有信心，可作出对于招标人有利的保证，靠此吸引招标人的注意。同时，工程监理单位需向招标人提出保证措施和惩罚性条款，确保承诺的可实施性。此策略适用于建设单位对工期等因素比较敏感的工程。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]