[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103982,780,1,"单选题","根据《标准监理招标文件(2017 年版)》，监理人应在接到开始监理通知之日起()天内，向委托人提交监理项目机构以及人员安排的报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","14","⑶监理人应在接到开始监理通知之日起7 天内，向委托人提交监理项目机构以及人员安排的报告，其内容应包括项目机构设置、主要监理人员和作业人员的名单及资格条件。主要监理人员应相对稳定，更换主要监理人员的，应取得委托人的同意，并向委托人提交继任人员的资格、管理经验等资料。除专用合同条款另有约定外，主要监理人员包括总监理工程师、专业监理工程师等；其他人员包括各专业的监理员、资料员等。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]