[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103900,780,1,"单选题","(2012年真题)下列建设工程监理委托模式中，要求监理单位具有较强的合同管理与组织协调能力的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在采用设计或施工总承包模式时，建设单位委托一家监理单位提供实施阶段全过程的监理服务",false,{"key":16,"text":17,"correct":14},"B","在采用设计或施工总承包模式时，建设单位按照设计阶段和施工阶段分别委托监理单位提供监理服务",{"key":19,"text":20,"correct":14},"C","在采用平行承发包模式时，建设单位委托多家监理单位提供监理服务",{"key":22,"text":23,"correct":24},"D","在采用平行承发包模式时，建设单位委托一家监理单位提供监理服务",true,"业主委托一家工程监理单位实施监理，要求被委托的工程监理单位应具有较强的合同管理与组织协调能力。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]