[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103889,780,1,"单选题","某工程分为两个子项目，合同总价为4800万美元，其中子项目一的合同价为2100万美元，子项目二的合同价为2700万美元，合同工期为32个月，则工程建设强度为()万美元／年。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1560",false,{"key":16,"text":17,"correct":14},"B","1280",{"key":19,"text":20,"correct":21},"C","1800",true,{"key":23,"text":24,"correct":14},"D","2400","2020版教材P102-106 本题考查的是项目监理机构人员配备及职责分工。 工程建设强度是指单位时间内投入的建设工程资金的数量，即：工程建设强度=投资／工期=4800／32×12=1800万美元／年。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]