[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103886,780,1,"单选题","建设工程平行承包模式的缺点包括( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主选择承包单位范围小",false,{"key":16,"text":17,"correct":18},"B","工程造价控制难度大",true,{"key":20,"text":21,"correct":14},"C","进度控制难度大",{"key":23,"text":24,"correct":14},"D","质量控制难度大","2020版教材P88-91 采用平行承包模式，由于各承包单位在其承包范围内同时进行相关工作，有利于缩短工期、控制质量，也有利于建设单位在更广范围内选择施工单位。但该模式的缺点是:合同数量多，会造成合同管理困难;工程造价控制难度大，表现为:一是工程总价不易确定，影响工程造价控制的实施;二是工程招标任务量大，需控制多项合同价格，增加了工程造价控制难度;三是在施工过程中设计变更和修改较多，导致工程造价增加。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]