[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103875,780,1,"单选题","下列工作中，总监理工程师可以将其委托给总监理工程师代表的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织审查和处理工程变更",true,{"key":16,"text":17,"correct":18},"B","组织编制监理规划，审批监理实施细则",false,{"key":20,"text":21,"correct":18},"C","签发工程款支付证书，组织审核竣工结算",{"key":23,"text":24,"correct":18},"D","签发工程开工令、暂停令和复工令","2020版教材P102-106 本题考查的是项目监理机构人员配备及职责分工。 总监理工程师不得将下列工作委托给总监理工程师代表：(1)组织编制监理规划，审批监理实施细则；(2)根据工程进展及监理工作情况调配监理人员；(3)组织审查施工组织设计、(专项)施工方案；(4)签发工程开工令、暂停令和复工令；(5)签发工程款支付证书，组织审核竣工结算；(6)调解建设单位与施工单位的合同争议，处理工程索赔；(7)审查施工单位的竣工申请，组织工程竣工预验收，组织编写工程质量评估报告，参与工程竣工验收；(8)参与或配合工程质量安全事故的调查和处理。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]