[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103863,780,1,"单选题","根据《建设工程监理规范》GB／T 50319—2013，工程监理单位调换专业监理工程师时，总监理工程师应()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","征得质量监督机构书面同意",false,{"key":16,"text":17,"correct":14},"B","征得建设单位书面同意",{"key":19,"text":20,"correct":14},"C","书面通知施工单位",{"key":22,"text":23,"correct":24},"D","书面通知建设单位",true,"2020教材P94-97 本题考查的是项目监理机构的设立。工程监理单位调换总监理工程师，应征得建设单位书面同意；调换专业监理工程师时，总监理工程师应书面通知建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]