[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103852,780,1,"单选题","建设工程施工完成以后，监理单位应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织工程竣工验收",false,{"key":16,"text":17,"correct":14},"B","与建设单位一起组织竣工验收",{"key":19,"text":20,"correct":21},"C","在正式验收前组织工程竣工预验收",true,{"key":23,"text":24,"correct":14},"D","与施工单位一起组织竣工验收","2020版教材P92 建设工程施工完成后，项目监理机构应在正式验收前组织工程竣工预验收。在预验收中发现的问题，应及时与施工单位沟通，提出整改要求。项目监理机构人员应参加由建设单位组织的工程竣工验收，签署工程监理意见。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]