[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103847,780,1,"单选题","（）是指单位时间内投入的建设工程资金的数量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程建设强度",true,{"key":16,"text":17,"correct":18},"B","工程建设工期",false,{"key":20,"text":21,"correct":18},"C","工程建设投资",{"key":23,"text":24,"correct":18},"D","建设工程复杂程度","2020版教材P103 工程建设强度是指单位时间内投入的建设工程资金的数量。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]