[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103840,780,1,"单选题","总监理工程师不得将下列（）工作委托给总监理工程师代表。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织召开监理例会",false,{"key":16,"text":17,"correct":14},"B","组织审核分包单位资格",{"key":19,"text":20,"correct":21},"C","组织编写工程质量评估报告",true,{"key":23,"text":24,"correct":14},"D","复核工程计量有关数据","2020版教材P105 具体而言，总监理工程师不得将下列工作委托给总监理工程师代表:（1）组织编制监理规划，审批监理实施细则；（2）根据工程进展及监理工作情况调配监理人员；（3）组织审查施工组织设计、（专项）施工方案；（4）签发工程开工令、暂停令和复工令；（5）签发工程款支付证书，组织审核竣工结算；（6）调解建设单位与施工单位的合同争议，处理工程索赔；（7）审查施工单位的竣工申请，组织工程竣工预验收，组织编写工程质量评估报告，参与工程竣工验收；（8）参与或配合工程质量安全事故的调查和处理。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]